Least Shocking News: DOTD Says LA1 Bridge Delayed 10-Months Due to Unexpected Settlement

Posted on 1/25/23 at 4:54 pm
Posted by lnomm34
Louisiana
Member since Oct 2009
12614 posts
Posted on 1/25/23 at 4:54 pm
LINK

quote:

Construction of the new LA 1 bridge over the Intracoastal Waterway in West Baton Rouge Parish will drag on up to 10 months longer than planned due to "unexpected settlement" of the structure.

Engineers say the issue concerns the piles under each of the 17 new bridge columns.

"(T)his issue will be mitigated using an alternative soil improvement technique called low-mobility grouting, whereby grout is injected into the ground beneath the piles to compact loose soils," the Department of Transportation and Development said.

quote:

Once both phases are completed, there will be a new southbound bridge that has three 12-foot lanes and 10-foot shoulders, and a new northbound bridge with two 12-foot lanes and 10-foot shoulders and a barrier-separated exit lane for I-10 eastbound.


quote:

The project was expected to cost about $58 million . . . . WBRZ News has reached out to DOTD asking whether the situation will affect the price the State pays for the new bridge.
Posted by CaptainsWafer
TD Platinum Member
Member since Feb 2006
58356 posts
Posted on 1/25/23 at 4:56 pm to
quote:

WBRZ News has reached out to DOTD asking whether the situation will affect the price the State pays for the new bridge.


Posted by 91TIGER
Lafayette
Member since Aug 2006
17717 posts
Posted on 1/25/23 at 5:03 pm to
And Shawn Wilson wants to be your Governor

This State is so f'n pathetic. Can't wait to leave it like the rest of the right minded people that have already gone.
Posted by FalseProphet
Mecca
Member since Dec 2011
11707 posts
Posted on 1/25/23 at 5:05 pm to
How in God’s name did the country build infrastructure in the 50s and 60s without problems that has lasted decades, but we can’t properly drive some damn pilings today?
Posted by PUB
New Orleans
Member since Sep 2017
18253 posts
Posted on 1/25/23 at 5:06 pm to
Millions upon millions in change orders due to engineers and contractors. Bend over and pay for it people.
This post was edited on 1/25/23 at 5:07 pm
Posted by Trout Bandit
Baton Rouge, LA
Member since Dec 2012
13276 posts
Posted on 1/25/23 at 5:10 pm to
Sounds like it's time for another study to me
Posted by Pu2kph0
Member since Oct 2022
1104 posts
Posted on 1/25/23 at 5:24 pm to
quote:

And Shawn Wilson wants to be your Governor


Can’t wait until he campaigns on the condition of Louisiana roads!
Posted by Hobie101
Member since May 2012
473 posts
Posted on 1/25/23 at 5:39 pm to
Low mobility grouting huh? They are crossing their fingers on this one
Posted by SantaFe
Baton Rouge
Member since Apr 2019
6583 posts
Posted on 1/25/23 at 5:45 pm to
Who ever performed the soil boring analysis for the pile locations did a phucked up job.
Posted by Tshiz
Idaho
Member since Jul 2013
7587 posts
Posted on 1/25/23 at 5:54 pm to
10 months and no price tag (yet)




Somethings fricky
Posted by Blutarsky
112th Congress
Member since Jan 2004
9669 posts
Posted on 1/25/23 at 5:55 pm to
Sounds like shitty Civil Engineering work to me.
Posted by The Boat
Member since Oct 2008
164235 posts
Posted on 1/25/23 at 5:55 pm to
Only LA1 bridge under construction I care about is Golden Meadow to Leeville baw
Posted by MrLSU
Yellowstone, Val d'isere
Member since Jan 2004
25994 posts
Posted on 1/25/23 at 6:10 pm to
quote:

Sounds like shitty Civil Engineering work to me.


It is clear as day from this article that Engineering hasn't yet caught up to Climate Change.
Posted by chRxis
None of your fricking business
Member since Feb 2008
23622 posts
Posted on 1/25/23 at 6:10 pm to
obligatory, it'll never be ready...
Posted by CaptainsWafer
TD Platinum Member
Member since Feb 2006
58356 posts
Posted on 1/25/23 at 6:11 pm to
quote:

Only LA1 bridge under construction I care about is Golden Meadow to Leeville baw



Saw this weekend that it’s started recently. When is it supposed to be finished.
Posted by PUB
New Orleans
Member since Sep 2017
18253 posts
Posted on 1/25/23 at 6:18 pm to
Exactly - and how many millions have they been paid?
Posted by upgrayedd
Lifting at Tobin's house
Member since Mar 2013
134865 posts
Posted on 1/25/23 at 6:20 pm to
I knew that construction was going way too smoothly. I've actually been impressed with the speed they've built that thing. Maybe this is why.
Posted by Jim Rockford
Member since May 2011
98197 posts
Posted on 1/25/23 at 6:33 pm to
Should have done a study first.
Posted by RougeDawg
Member since Jul 2016
5875 posts
Posted on 1/25/23 at 6:41 pm to
quote:

Engineers say the issue concerns the piles under each of the 17 new bridge columns.


ALL of the piles are settling before they even loaded it?!

Better buy some more ferries.
Posted by Blutarsky
112th Congress
Member since Jan 2004
9669 posts
Posted on 1/25/23 at 6:47 pm to
quote:

Exactly - and how many millions have they been paid?


We were joking a few years ago about DOTD Civil Engineers on massive bridge projects. It takes around 10 years from start to finish once a site is selected.

What do you do for 10 years? frick off for 9.5 years and then look for a new job the other 6 months?
first pageprev pagePage 1 of 2Next pagelast page

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on Twitter, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookTwitterInstagram