Comite Diversion Canal groundbreaking held this week, expected to be done by 2021

Posted on 4/18/19 at 7:24 pm
Posted by member12
Bob's Country Bunker
Member since May 2008
33036 posts
Posted on 4/18/19 at 7:24 pm
quote:

LINK

Lawmakers broke ground Wednesday, April 17 on the long-awaited Comite River Diversion Canal project that could save thousands in the capital region time and money by lowering floodwater.

The canal will drain the Comite into the Mississippi during high-water events, potentially mitigating flooding in the entire Baton Rouge region, but particularly aiding residents in Livingston and northern East Baton Rouge parishes.


quote:

The project found more than $300 million in federal funding when Congress prioritized flood mitigation after devastating hurricanes in Texas, Puerto Rico, and Florida.

"We got to step up and say, ‘Wait a second. What about the Great Flood of 2016?' U.S. Senator Bill Cassidy said. "If you look at the dollar value of the damage, and the lives and families so powerfully affected, there’s as much a case to be made to address that issue as for the surrounding hurricanes.”

The project was proposed in the late 1970s, and lawmakers broke ground on a $30 million portion of the project in 2003 at Lilly Bayou. It sits mostly useless now, but will be tied into the final structure.


Louisiana takes 30 years to dig a ditch, thanks to environmental red tape.....but there is light at the end of the tunnel finally.
Posted by fightin tigers
Downtown Prairieville
Member since Mar 2008
76144 posts
Posted on 4/18/19 at 7:26 pm to
quote:

but there is light at the end of the tunnel finally.


Oh, sweetie.
Posted by upgrayedd
Lifting at Tobin's house
Member since Mar 2013
138059 posts
Posted on 4/18/19 at 7:30 pm to
8/20/19 - "Comite River Diversion Canal project administrators request additional funds as they claim the project is in danger of running out of money after only 4 months. Expected completion date now estimated to be March of 2029"
Posted by Martini
Near Athens
Member since Mar 2005
49616 posts
Posted on 4/18/19 at 7:37 pm to
If by chance they could get the funds and environmental done to build the Darlington Reservoir that would be icing on the cake.
Posted by Purple Spoon
Hoth
Member since Feb 2005
20184 posts
Posted on 4/18/19 at 7:42 pm to
quote:

expected to be done by 2121


That’s better
Posted by Halftrack
The Wild Blue Yonder
Member since Apr 2015
2763 posts
Posted on 4/18/19 at 7:46 pm to
New places for camps??
Posted by tigerbutt
Deep South
Member since Jun 2006
26094 posts
Posted on 4/18/19 at 8:14 pm to
It’ll never be ready in time.
Posted by soccerfüt
Location: A Series of Tubes
Member since May 2013
72722 posts
Posted on 4/18/19 at 8:25 pm to
quote:

expected to be done by 2021
Dateline 4/18/2022:

Comite Diversion Canal Is Sinking
Posted by Bulldozer1899
Member since Aug 2017
165 posts
Posted on 4/18/19 at 8:25 pm to
Which out of state construction company this project?
Posted by soccerfüt
Location: A Series of Tubes
Member since May 2013
72722 posts
Posted on 4/18/19 at 8:29 pm to
quote:

Which out of state construction company this project?
Thank you for posting Master Yoda.


Posted by Obtuse1
Westside Bodymore Yo
Member since Sep 2016
30017 posts
Posted on 4/18/19 at 9:27 pm to
quote:

New places for camps??


The landowners/developers on the canal will make a mint when it is finished just like the ones around the Amite Diversion.
Posted by ecb
Member since Jul 2010
10085 posts
Posted on 4/18/19 at 9:33 pm to
How does this work if the Miss River happens to be high?
Posted by Tarps99
Lafourche Parish
Member since Apr 2017
11458 posts
Posted on 4/18/19 at 10:19 pm to
quote:

How does this work if the Miss River happens to be high?


I would assume there are huge pumps that would push the water in the river.

Question from a coastal restoration stand point, in dry times couldn’t this system work backwards and help the salinity levels in Lake Maurepas?
Posted by pensacola
pensacola
Member since Sep 2005
4797 posts
Posted on 4/18/19 at 10:28 pm to
quote:

How does this work if the Miss River happens to be high?

The engineers would not comite.
Posted by BeepNode
Lafayette
Member since Feb 2014
10005 posts
Posted on 4/18/19 at 10:51 pm to
What's incredible was that some of the very politicians that are championing this project are the same ones that blocked in previous decades because they were working on real estate deals for themselves and their families. Some of these politicians bought land that they wanted the government to buy from them for the canal project, but the fear was that they'd use eminent domain.

Even in 2010 Bodi White got a bill passed that prevented the feds from using eminent domain in order to complete the project after it already started, which means they needed to find a contiguous string of properties with willing sellers and all it would take is one or two hold-outs to drive the prices up. In fact, that's what happened. Some of the land had been purchased but they couldn't get a clear path across.

The head of the Amite River Basic Commission lamented back in 2011 or so that a big flood was going to happen and then they'd be begging for eminent domain anyway so he was trying to urge everyone to act reasonable. It didn't help that the legal council for the ARBC was a known crook who had just gotten out of Federal prison.

This stuff should be more interesting and noteworthy to people around here than it is.
Posted by zmonsoon
"The LP"
Member since Nov 2007
907 posts
Posted on 4/18/19 at 11:10 pm to
I cant even be mad right now. What did I expect from Louisiana political leadership.

Why the frick do I live here?!

This is an increasingly difficult question to answer.

Posted by MrLSU
Yellowstone, Val d'isere
Member since Jan 2004
28967 posts
Posted on 4/19/19 at 1:32 am to
DOTD will build a boat launch on the Comite Division Canal by 2040. Boat access to be restricted until further notice.
Posted by johnnyrocket
Ghetto once known as Baton Rouge
Member since Apr 2013
9790 posts
Posted on 4/19/19 at 6:50 am to
Then been talking about the Darlington Reservoir and canal since 80’s right when I left this area.

If I am correct they studied the reservoir and said land was not stable enough to build a reservoir. I remember my father telling me if that reservoir was built a lot of the guys hoped the fishing would be good.

I’ll probably never see it in my lifetime or the Comite diversion canal. They will find and excuse resulting in more delays due to needing more money.
This post was edited on 4/19/19 at 6:52 am
Posted by Vastmind
B Ara
Member since Sep 2013
5322 posts
Posted on 4/19/19 at 7:08 am to
That’s gonna be some good fishing baw
Posted by BottomlandBrew
Member since Aug 2010
29200 posts
Posted on 4/19/19 at 7:15 am to
quote:

Louisiana takes 30 years to dig a ditch, thanks to environmental red tape


The environmental red tape was the least of the problems holding that project back. It was held up thanks to the ever-so-component leadership in the region.
first pageprev pagePage 1 of 2Next pagelast page

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on X, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookXInstagram