re: Bourbon street construction nearly 3x over budget

Posted on 2/1/18 at 12:20 pm to
Posted by tgrbaitn08
Member since Dec 2007
148031 posts
Posted on 2/1/18 at 12:20 pm to
quote:

I could imagine how the bid process went. Contractors show up to look around and are given some half assed drawings with little to no detail. Hell, there probably aren't even any records worth a damn going back more than 20 years on what's under Bourbon.
So the guys break ground and start finding all kinds of piping, electrical, sewage stuff there was not expected.





but they learned their lesson
Posted by AbitaFan08
Boston, MA
Member since Apr 2008
27902 posts
Posted on 2/1/18 at 12:20 pm to
Wonder what the final body count will be once all the digging is done.

Vegas has 12/1 odds that Jimmy Hoffa is going to finally be found.
Posted by Agforlife
Somewhere in the Brazos Valley
Member since Nov 2012
20102 posts
Posted on 2/1/18 at 12:20 pm to
quote:

Ohh i agree but you have to allot time for that shite



But if you do that you'll never win a bid. You bid on the shitty plans you get and hope for the best and if you run into problems it's change order time.
Posted by Saskwatch
Member since Feb 2016
18319 posts
Posted on 2/1/18 at 12:21 pm to
quote:

skyrocketed from an original estimate of $6 million last spring to $13 million in August, and now to $17 million.


Posted by UncleRuckus
Member since Feb 2013
10200 posts
Posted on 2/1/18 at 12:21 pm to
This is surprising to no one. Louisiana is a shite hole because of crooked arse politics
Posted by soccerfüt
Location: A Series of Tubes
Member since May 2013
75820 posts
Posted on 2/1/18 at 12:21 pm to
quote:

Dani Galloway, the interim director of the city's Department of Public Works
Meh, IWNHI
Posted by starsandstripes
Georgia
Member since Nov 2017
11897 posts
Posted on 2/1/18 at 12:22 pm to
quote:

Bourbon street


Shithole
Posted by LSUBoo
Knoxville, TN
Member since Mar 2006
104329 posts
Posted on 2/1/18 at 12:23 pm to
quote:

So it's now over 4X the original bid. What's even the point of the bid process when you can change order that much?



Posted by upgrayedd
Lifting at Tobin's house
Member since Mar 2013
139145 posts
Posted on 2/1/18 at 12:23 pm to
quote:

You bid on the shitty plans you get and hope for the best and if you run into problems it's change order time.



Honestly, if you were going to try to run cover for some corruption, this is probably as close to a perfect scenario as it gets.
Posted by upgrayedd
Lifting at Tobin's house
Member since Mar 2013
139145 posts
Posted on 2/1/18 at 12:23 pm to
Posted by Wtodd
Tampa, FL
Member since Oct 2013
68594 posts
Posted on 2/1/18 at 12:24 pm to
quote:

3x over budget

shite that's a bargain for you guys....props
Posted by TH03
Mogadishu
Member since Dec 2008
172004 posts
Posted on 2/1/18 at 12:25 pm to
Does the small one say original contract?
Posted by Ben Hur
Baton Rouge, LA
Member since Feb 2013
1014 posts
Posted on 2/1/18 at 12:25 pm to
quote:

quote:

Bourbon street


Shithole


Hence the need for a renovation..
Posted by LSUBoo
Knoxville, TN
Member since Mar 2006
104329 posts
Posted on 2/1/18 at 12:25 pm to
quote:

Does the small one say original contract?


Yes.
Posted by Saskwatch
Member since Feb 2016
18319 posts
Posted on 2/1/18 at 12:27 pm to
I hope they pave the street in whatever they make those piss pucks out of. It would give it a fresh scent smell.
Posted by TH03
Mogadishu
Member since Dec 2008
172004 posts
Posted on 2/1/18 at 12:27 pm to
That's great.
Posted by Agforlife
Somewhere in the Brazos Valley
Member since Nov 2012
20102 posts
Posted on 2/1/18 at 12:28 pm to
quote:

Honestly, if you were going to try to run cover for some corruption, this is probably as close to a perfect scenario as it gets.


Yep, most of the time the plans we get are pretty straightforward but I've had some nightmare projects too.
Posted by StealthCalais11
Lurker since 2007
Member since Aug 2011
12553 posts
Posted on 2/1/18 at 12:28 pm to
It'll be back to bourbon Street standards within a month
Posted by Brazoria Bengal
Your Wildest Dreams
Member since Nov 2016
112 posts
Posted on 2/1/18 at 12:34 pm to
BR > NOLA

Mayor SWB would have spent $5 million on an assessment executed by Southern University officials LONG before they broke ground on such a project and started increasing their EAC as every day passes.

SWB > ML
Posted by YoungManOldMan
Member since Dec 2017
1882 posts
Posted on 2/1/18 at 12:36 pm to
Knowing how this stuff works, the city is incompetent to accept a bid 1M under everyone else without vetting everything completely before signing the contract.

Differing site conditions matter and they should be entitled to an equitable adjustment for those problem, but to tack on more work in scope to an existing maitnence agreement is bad public procurement practice.

This is incompetence in action, not necessarily fraud.
This post was edited on 2/1/18 at 12:37 pm
first pageprev pagePage 2 of 5Next pagelast page

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on X, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookXInstagram