- My Forums
- Tiger Rant
- LSU Recruiting
- SEC Rant
- Saints Talk
- Pelicans Talk
- More Sports Board
- Coaching Changes
- Fantasy Sports
- Golf Board
- Soccer Board
- O-T Lounge
- Tech Board
- Home/Garden Board
- Outdoor Board
- Health/Fitness Board
- Movie/TV Board
- Book Board
- Music Board
- Political Talk
- Money Talk
- Fark Board
- Gaming Board
- Travel Board
- Food/Drink Board
- Ticket Exchange
- TD Help Board
Customize My Forums- View All Forums
- Show Left Links
- Topic Sort Options
- Trending Topics
- Recent Topics
- Active Topics
Started By
Message
Does anyone have knowledge on the roadwork on Sullivan Rd between Wax and Hooper?!
Posted on 8/5/25 at 7:57 pm
Posted on 8/5/25 at 7:57 pm
How long has that been going on?
WTH? Is it 10, 15, 20 years?
That part of the highway a long with the corner of Sullivan and Hooper has turned into a complete shite hole.
WTH? Is it 10, 15, 20 years?
That part of the highway a long with the corner of Sullivan and Hooper has turned into a complete shite hole.
Posted on 8/5/25 at 8:01 pm to SmackDaniels
They were delayed a long time but have been busting arse lately
Posted on 8/5/25 at 8:16 pm to SmackDaniels
Seeage and drainage is a biatch
Posted on 8/5/25 at 9:12 pm to SmackDaniels
I would say it’s probably been about 10 years
Posted on 8/5/25 at 9:16 pm to LSUJML
quote:
They were delayed a long time
It's like they started 10 years ago and it really seems like they haven't done a damn thing, and I mean NOT A DAMN thing since.
Posted on 8/5/25 at 9:17 pm to thegambler
quote:
Seeage and drainage is a biatch
I have heard that too but did they just give up?
Posted on 8/5/25 at 9:19 pm to SmackDaniels
I mean big sections of new road is pretty good considering how long the project was halted
They are out there 7 days a week & pouring concrete at night
I’m not 100% but it was a drainage issue between state, engineers, drainage board….maybe when they started they realized what they planned for wouldn’t work
Basically years & years of the blame game & who was at fault & how to proceed
They are out there 7 days a week & pouring concrete at night
quote:
I have heard that too but did they just give up?
I’m not 100% but it was a drainage issue between state, engineers, drainage board….maybe when they started they realized what they planned for wouldn’t work
Basically years & years of the blame game & who was at fault & how to proceed
This post was edited on 8/5/25 at 9:22 pm
Posted on 8/5/25 at 9:26 pm to SmackDaniels
Was going on before my daughter went into the first grade at Tanglewood. She starts her jr year in high school on Thursday!!
Posted on 8/5/25 at 9:30 pm to SmackDaniels
It’s ridiculous how long it takes to fix a problem with a road. I believe the intersection at Sullivan and Hooper was terrible before they started…
Posted on 8/6/25 at 9:06 am to Pepe Lepew
I live in Florida. My parents still live in Central off Gurney. I come to visit parents and everytime I come in it’s exactly the same for the past 15 years. Saying that, they actually lare laying concrete like some of you have mentioned.
Posted on 8/6/25 at 9:07 am to SmackDaniels
Wade going to get some arse at DOTD if they don't get to moving.
Posted on 8/6/25 at 9:52 am to SmackDaniels
quote:
It's like they started 10 years ago and it really seems like they haven't done a damn thing, and I mean NOT A DAMN thing since.
They stopped work for a while when they couldn't figure out where groundwater was coming from.
What sucks is they didn't finish Sullivan before getting started on Wax so the whole area is a traffic shitshow that is about to get a lot worse with school starting.
Posted on 8/6/25 at 1:37 pm to SmackDaniels
It's pathetic. Was part of central's initial strategic plan, backed by "a traffic study" [performed nearly 20 years ago] to have sullivan widened, have hooper widened, and have wax widened.
All should have been done YEARS ago.
Matter of fact, they should also have a hooper rd to watson (LA1019 or LA16) bridge in place by now, too.
P&Z/council/mayor keep allowing residential development and keep screwing up logical necessary infrastructure improvements. But they got that city hall going in on the donated schoolboard property.
All should have been done YEARS ago.
P&Z/council/mayor keep allowing residential development and keep screwing up logical necessary infrastructure improvements. But they got that city hall going in on the donated schoolboard property.
This post was edited on 8/6/25 at 1:38 pm
Posted on 8/6/25 at 2:00 pm to SmackDaniels
It’s actually going pretty quick now.
They had a few redesigns I believe and had to wait on sewer utilities to be completed.
They had a few redesigns I believe and had to wait on sewer utilities to be completed.
Popular
Back to top
9