re: OT Plant workers - how’s your facility handling the new supply chain issues?

Posted on 1/12/22 at 5:56 pm to
Posted by Duct6slayer
Member since Sep 2017
10 posts
Posted on 1/12/22 at 5:56 pm to
In Industrial Pipe fabrication. Quotes only good for 2 days on pipe/valves/fittings. Alloys 6-8 wks. Paint is 3-4 wks out. Hotshot service from Houston to SWLA is insane. And the customers don't care. Build it as fast as you can.