OK, I want to get a 12x24 concrete pad poured and I have absolutely zero knowledge in this area. What are some things I need to ask and things to look out for so I won't get scammed? A ballpark price range would also be nice. TIA
Posted by Penn
Jax Beach
Member since Jan 2008
23721 posts
Posted on 10/8/26 at 7:02 pm to
Following
Posted by GeauxTime9
Baton Rouge, La
Member since Dec 2010
7142 posts
Posted on 10/8/26 at 7:16 pm to
Assuming 4” with wire mesh, you probably looking at $3kish pending location and pre-form needs.
Posted by GumboPoBoy
Member since Jun 2015
359 posts
Posted on 10/8/26 at 7:46 pm to
Where are you located?
What’s going on top of it?

6-8” is always enough or maybe too much…
Posted by Jcharles
Member since Sep 2026
64 posts
Posted on 10/8/26 at 8:33 pm to
What kind of access does the area have?
Posted by mach316
Northeast Arkansas
Member since Jul 2012
4967 posts
Posted on 10/8/26 at 8:42 pm to
Go 6” imo. Can’t help you on price. Ask around, and find a reputable contractor.
Posted by Barneyrb
NELA
Member since May 2016
7523 posts
Posted on 10/8/26 at 8:56 pm to
Are you building on it, if so you're going to need footers and depending on type of building will dictate size of footer.

Light traffic or heavy (cars, trucks, tractors) dictate the thickness.

Posted by Sparty3131
Baton Rouge
Member since Feb 2019
1036 posts
Posted on 10/9/26 at 7:43 am to
Access to the location. DO NOT let a loaded concrete truck drive down a 4" thick driveway. So if you need a line pump or georgia buggy that will add to the cost. Cheaper if they can tailgate.

Like others said. You will need footers if you are building on top of it. I would do 6" thick if it was me. It is about 2yds of concrete different compared to 4"; maybe $400-450 more depending on the price of mud.

I got qouted $1200 for the finish alone for a pour that needed a georgia buggy in April. Was a little smaller than your pour. Fair price. Even a small pour like this will take 3 people or 2 really good finishers. Pulling a screed, bull float, comalongs, running the buggy.

Concrete will be at least $1000, they charge a base for sending a truck; even if it is not loaded with a full 9/10 yds.

Turn key with dirt work and forms hung I would guess: $4500-6000. I would have did the dirt works and forms myself so I am guessing on the cost for that.


This post was edited on 10/9/26 at 12:44 pm
Posted by HeadSlash
TEAM LIVE BADASS - St. GEORGE
Member since Aug 2006
57034 posts
Posted on 10/9/26 at 8:42 am to
quote:

6-8” is always enough or maybe too much…


It's never enough. I'm a firm believer in overkill.
Posted by riseabovethenoise
Member since Jul 2026
32 posts
Posted on 10/9/26 at 4:51 pm to
I'm located about an hour north of Mobile, Alabama. The plan is to put a pergola over half of it, so I can watch some games and enjoy the outside and the other half have a grill and some storage, but I'm not doing that until this summer.

Some people are saying wire mesh or rebar. Is one much better than the other?

What do I need to ask to try and avoid getting a bad concrete guy? Also, is payment done after the job or some money up front?

How long should I expect it to take from start to finish?

TIA
first pageprev pagePage 1 of 1Next pagelast page
refresh

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on X, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

Facebook•X•Instagram