- My Forums
- Tiger Rant
- LSU Recruiting
- SEC Rant
- Saints Talk
- Pelicans Talk
- More Sports Board
- Coaching Changes
- Fantasy Sports
- Golf Board
- Soccer Board
- O-T Lounge
- Tech Board
- Home/Garden Board
- Outdoor Board
- Health/Fitness Board
- Movie/TV Board
- Book Board
- Music Board
- Political Talk
- Money Talk
- Fark Board
- Gaming Board
- Travel Board
- Food/Drink Board
- Ticket Exchange
- TD Help Board
Customize My Forums- View All Forums
- Show Left Links
- Topic Sort Options
- Trending Topics
- Recent Topics
- Active Topics
Started By
Message
Posted on 11/25/26 at 11:39 am to Fe_Mike
What do you see the chances of FID actually come through ? Claude has it at 50/50 and lists these reasons
To be upfront: that number is my judgment, not the output of a model or an analyst figure. No source puts odds on it. I weighed a handful of facts, and someone else could look at the same facts and say 40% or 60%.
What pulls it toward a coin flip or lower:
• Their track record. Four FID targets missed or abandoned across two projects. SWA moved from early 2026 to during 2026 to year-end to Q1 2027. Each time management sounded confident, and each time it slipped another three to six months. A forecast should lean on that pattern, not on the latest promise.
• The calendar. Q1 ends about 4.5 months from now, and the holidays fall in that window. The remaining steps include three separate government lenders each getting formal committee approval, plus negotiating overrun and reserve terms, plus signing documents.
• The EXIM review step. If I'm right that a loan this size needs a congressional notice period before EXIM's board votes, that's weeks of fixed time they can't speed up.
• The pressure to hit this date is weaker. The $40 million Equinor payment depended on beating January 1. It's already lost, so missing Q1 by a month or two costs them less than missing that deadline did.
What pulls it up:
• Diligence is "substantially complete," and the customers, contracts and permits are all done. Money is the only open item.
• Management knows more than we do. They set Q1 after already being burned once, so they may have built in some cushion.
• They spend roughly $10–15 million a quarter, much of it through the joint venture, so they still have every reason to close quickly.
To be upfront: that number is my judgment, not the output of a model or an analyst figure. No source puts odds on it. I weighed a handful of facts, and someone else could look at the same facts and say 40% or 60%.
What pulls it toward a coin flip or lower:
• Their track record. Four FID targets missed or abandoned across two projects. SWA moved from early 2026 to during 2026 to year-end to Q1 2027. Each time management sounded confident, and each time it slipped another three to six months. A forecast should lean on that pattern, not on the latest promise.
• The calendar. Q1 ends about 4.5 months from now, and the holidays fall in that window. The remaining steps include three separate government lenders each getting formal committee approval, plus negotiating overrun and reserve terms, plus signing documents.
• The EXIM review step. If I'm right that a loan this size needs a congressional notice period before EXIM's board votes, that's weeks of fixed time they can't speed up.
• The pressure to hit this date is weaker. The $40 million Equinor payment depended on beating January 1. It's already lost, so missing Q1 by a month or two costs them less than missing that deadline did.
What pulls it up:
• Diligence is "substantially complete," and the customers, contracts and permits are all done. Money is the only open item.
• Management knows more than we do. They set Q1 after already being burned once, so they may have built in some cushion.
• They spend roughly $10–15 million a quarter, much of it through the joint venture, so they still have every reason to close quickly.
Posted on 11/25/26 at 1:55 pm to dstone12
It’s entirely dependent on lithium pricing. Market is currently below the FEED economics which is what is causing the delay.
We’re heavily gov driven right now (until the FID is made). Frankly, the economics aren’t good at this snapshot in time, but that’s not the deciding factor. The price is still really conservative at $20k/ton (although lithium is currently 35% below that), and I think it still gets done, but there is more risk the longer lithium prices stay low.
Assuming they pull the trigger, $8-10/share in 2030 is reasonable if lithium prices get back to conservative $20k/ton levels.
If lithium rebounds for whatever reason back to the $40k/ton range, after FID is made, we could go bananas and break $20 by 2030 depending on the offtake structure.
ETA:
But to be clear, the binary has become much more risky than a year ago. FID used to be baked in. With lithium prices low it no longer is. The reason for the delay is absolutely on the lender(s) balking at lithium prices. If they don’t start rebounding soon, we’ll see more delays and start getting hit by dilution.
We’re heavily gov driven right now (until the FID is made). Frankly, the economics aren’t good at this snapshot in time, but that’s not the deciding factor. The price is still really conservative at $20k/ton (although lithium is currently 35% below that), and I think it still gets done, but there is more risk the longer lithium prices stay low.
Assuming they pull the trigger, $8-10/share in 2030 is reasonable if lithium prices get back to conservative $20k/ton levels.
If lithium rebounds for whatever reason back to the $40k/ton range, after FID is made, we could go bananas and break $20 by 2030 depending on the offtake structure.
ETA:
But to be clear, the binary has become much more risky than a year ago. FID used to be baked in. With lithium prices low it no longer is. The reason for the delay is absolutely on the lender(s) balking at lithium prices. If they don’t start rebounding soon, we’ll see more delays and start getting hit by dilution.
This post was edited on 11/25/26 at 2:00 pm