re: OT help with construction loan process

Posted on 10/11/21 at 11:36 pm to
Posted by dallasaggie
Dallas
Member since May 2013
949 posts
Posted on 10/11/21 at 11:36 pm to
My team lends money to commercial developers including home builders. We don’t lend to individuals… that said… no. You put your 20 down on the land. I’m not lending on materials until the work is in place … those things can walk off the job site. Think of it this way. After closing… you put up the work, the bank inspects then it funds.

We also do percentage of completion method. Not invoices. So if you’re over budget on a line item, you’re paying the difference then. Can’t do it off of invoices and the project goes over budget and you don’t have the money to finish after the loan is fully funded.
Posted by shoelessjoe
Member since Jul 2006
9926 posts
Posted on 10/12/21 at 1:07 am to
The materials will be stored at the warehouse by the supplier. Already talked about that to them. So if I have say 115k which is over 20% of total cost of home plus I own the land, I am not allowed to use the 20% I already have, to purchase materials and have them stored at warehouse until loan is finalized? I am only talking for about 6-8 weeks before I am ready to start. Materials are already at warehouse waiting for me to say bring them builders are here. Not like it will be stolen or walking off.
This post was edited on 10/12/21 at 1:13 am
first pageprev pagePage 1 of 1Next pagelast page
refresh

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on Twitter, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookTwitterInstagram