Apparently, construction on the exit/entrance ramps for this project will not even begin for another 2-3 years. They haven’t even began the bidding process on phase 3. This is a project that started in 2017 and probably will not be completed until after 2017. Pathetic…but very typical of LA. Any other state would have had this completed in 2 years.

quote:

Mallett says up next is on and off-ramps to access I-10 from Pecue. However, construction isn't set to start any time soon.

"The next phase is yet to be bid, so once that gets bid we'll go and start phase three," Mallett said. "That's estimated to be two to three years."


LINK
This post was edited on 2/4/22 at 7:17 am
Posted by NPComb
Member since Jan 2019
27570 posts
Posted on 2/4/22 at 7:29 am to
Only in Louisiana can we make an almost rural off ramp construction project seem like the Big Dig.
Posted by PhiTiger1764
Lurker since Aug 2003
Member since Oct 2009
13961 posts
Posted on 2/4/22 at 8:40 am to
quote:

Pathetic…but very typical of LA. Any other state would have had this completed in 2 years.

Literally from your own link that you posted, they say they don’t want to build Interstate ramp access until Pecue is 4 lanes from Airline to Perkins. So that has to be constructed first. It is planned out this way.

I swear some of y’all just love to complain.
first pageprev pagePage 1 of 1Next pagelast page
refresh

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on Twitter, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookTwitterInstagram