re: Malletinc, Pole barn buildings.

Posted on 10/23/21 at 10:39 am to
Posted by Werner11122020
Member since Oct 2021
24 posts
Posted on 10/23/21 at 10:39 am to
1) Communication with Lee Mallett's employees is a nightmare.
2) Lee Mallett's building framer missed the building elevation 10" to high, which will cost me.
3) Due to recent damage from Hurricane Ida I learned that my #1 Mallett building was put together with nails instead of screws.
4) To many problems to list them all here.
This post was edited on 10/23/21 at 11:56 am
Posted by X123F45
Member since Apr 2015
28051 posts
Posted on 10/23/21 at 11:27 am to
quote:

I learned that my #1 Mallett building was put together with nails instead of screws.


You are now to be ignored....
Posted by back9Tiger
Mandeville, LA.
Member since Nov 2005
14517 posts
Posted on 10/29/21 at 4:03 pm to
We build buildings for a living. This....


2) Lee Mallett's building framer missed the building elevation 10" to high, which will cost me.

Is on the contractor. If it was a lump sum price, no way you accept that change.
first pageprev pagePage 1 of 1Next pagelast page
refresh

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on Twitter, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookTwitterInstagram