It's October now, and my patience is wearing thin. Anyone had better luck than me?


Optimize was doing yearly service on my 25kw liquid cooled generac, was talking with the tech and he said the 22kw air cooled down to the 7kw are backlogged to feb/mar 2022..the liquid cooled is about 2 weeks wait time. In 2017 my 25kw ((LC) was right at 14,000 installed with other options. The same 25kw installed now is right at 20,000.