quote:

He said I run a serious risk of the whole damn roof caving in if I remove those headers.


Not with a good temporary shoring plan, but you gotta pay extra for that if you can even find someone able and willing to assume liability.

ETA:
quote:

You need to remove the headers and use a double 2"x 12" or glue lam to span the distance.

LVL or parallam will handle more load and it's cheaper. Glulams are good for exposed members.
This post was edited on 3/21/17 at 3:29 pm