re: Cranes going up for the SEZ expansion (Updated)

Posted on 3/14/13 at 4:16 pm to
Posted by tigeraddict
Baton Rouge
Member since Mar 2007
11882 posts
Posted on 3/14/13 at 4:16 pm to
quote:

At LSU this always takes longer than it should. I wish they would just go ahead and hire me to create as-built models for them.


that's the problem. even LSU doesn't know whats underground. they hit so many underground utilities trying to drive in pylons it slowed the process down. and the rain the past few months has turned the site into a slop hole....

you should see it roll once the get out of the ground
Posted by junkfunky
Member since Jan 2011
34035 posts
Posted on 3/14/13 at 4:27 pm to
quote:

that's the problem. even LSU doesn't know whats underground. they hit so many underground utilities trying to drive in pylons it slowed the process down. and the rain the past few months has turned the site into a slop hole....


This is the reason the Union project took so damn long. The other recent projects I know of that are more to the East and North of the Union didn't have many issues at all but the area between the Union and stadium is damn mess.

I think (but I'm not positive) they used GPR (ground penetrating radar) and I know they used an above ground laser system (total-station or equivalent) when they were doing the cost estimate. As far as I know it's the only project to use these (fairly new technologies) so they were aware of the issues before they even broke ground.

quote:

you should see it roll once the get out of the ground


Heck yeah. With 3 cranes, steel's gonna be going up quick, but then it'll seem to kinda hit a lull once the above ground concrete work gets rolling.

I'm pretty excited about this project.
first pageprev pagePage 1 of 1Next pagelast page
refresh

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on Twitter, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookTwitterInstagram