no shite? I was laughing because your post made it seem you thought it took months to build the foundations just for the cranes.


Of course they don't take that long to get one operational if really needed. You could probably have the piling done in a day, the formwork done in a few days and ready to pour and then at least 7 days for the breaks. So within 2 weeks you can have all 3 operational if you put enough man power behind but that's not what usually happens and isn't what happened on this project. They took at least a month and half, probably longer from start to finish.
This post was edited on 3/14/13 at 1:27 pm
Posted by contactmo
Member since Jan 2012
131 posts
Posted on 3/14/13 at 1:41 pm to
In case no one knew it existed... Images are from noon noon the previous day.

LINK
This post was edited on 3/14/13 at 1:42 pm
Posted by MRTigerFan
Baton Rouge
Member since Sep 2008
4247 posts
Posted on 3/14/13 at 1:41 pm to
quote:

Of course they don't take that long to get one operational if really needed. You could probably have the piling done in a day, the formwork done in a few days and ready to pour and then at least 7 days for the breaks. So within 2 weeks you can have all 3 operational if you put enough man power behind but that's not what usually happens and isn't what happened on this project. They took at least a month and half, probably longer from start to finish.


How dare you bring that kind of accurate knowledge and actually state facts on the rant! GTFO
first pageprev pagePage 1 of 1Next pagelast page
refresh

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on Twitter, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookTwitterInstagram