re: Entergy Submitts Plans to Build a Floating Power Plant in Leeville

Posted on 3/7/24 at 9:54 am to
Posted by Cosmo
glassman's guest house
Member since Oct 2003
120802 posts
Posted on 3/7/24 at 9:54 am to
quote:

black-start capability


Posted by Tarps99
Lafourche Parish
Member since Apr 2017
7768 posts
Posted on 3/7/24 at 10:03 am to
quote:

black-start capability


I never knew this until a few years ago.

You need a smaller power plant to start a larger one.

A year or 2 before Ida, Terrebonne Parish installed 3 1 MW generators to add to the Houma plant to get it started when they lost their tie in to Entergy. So they would have to RENT the 3 1 MW units each disaster to start the plant after a hurricane.