- My Forums
- Tiger Rant
- LSU Recruiting
- SEC Rant
- Saints Talk
- Pelicans Talk
- More Sports Board
- Fantasy Sports
- Golf Board
- Soccer Board
- O-T Lounge
- Tech Board
- Home/Garden Board
- Outdoor Board
- Health/Fitness Board
- Movie/TV Board
- Book Board
- Music Board
- Political Talk
- Money Talk
- Fark Board
- Gaming Board
- Travel Board
- Food/Drink Board
- Ticket Exchange
- TD Help Board
Customize My Forums- View All Forums
- Show Left Links
- Topic Sort Options
- Trending Topics
- Recent Topics
- Active Topics
Started By
Message
Microsoft Project Experts
Posted on 6/3/14 at 10:15 am
Posted on 6/3/14 at 10:15 am
Is it possible to show a range for task duration?
If yes, how?
Some tasks can take between 8 to 12 weeks depending on numerous outside variables so I don't want to lock myself down for one duration.
How do I best go about showing a range for duration?
I've used the almighty google but can't seem to find what I need.
If yes, how?
Some tasks can take between 8 to 12 weeks depending on numerous outside variables so I don't want to lock myself down for one duration.
How do I best go about showing a range for duration?
I've used the almighty google but can't seem to find what I need.
Posted on 6/3/14 at 10:46 am to TigerMyth36
Upgrade to Primavera. Stop using an inferior product.