Construction guys: question re: Jefferson/Bluebonnet project

Posted on 7/7/25 at 3:10 pm
Posted by King of New Orleans
In front of The Hungry Tiger
Member since Jul 2011
11024 posts
Posted on 7/7/25 at 3:10 pm
I drive this stretch of Jefferson Hwy multiple times during the week. It’s unreal how often I drive through and see absolutely zero workers.

Why is this? This has to play into why jobs like this take so long, right?

I rarely see anyone out there even at night.

What gives? Truly interested.
Posted by Aspercel
Member since Jan 2009
117492 posts
Posted on 7/7/25 at 3:13 pm to
About every two weeks they take out the access bridges for a few hours, then rebuild them hours later. As far as I know that is the only work they do. Usually with no notice.

Oh, and they pump out the lakes that form when it rains.
Posted by BurningHeart
Member since Jan 2017
10068 posts
Posted on 7/7/25 at 3:14 pm to
quote:

What gives? Truly interested.


1) Tear up existing road - 2 weeks

2) Plan next steps - 4 months

3) Repave a small section - 2 weeks

4) Plan next steps - 6 months

5) Finish road - 2 weeks
Posted by BilbeauTBaggins
Member since May 2021
7669 posts
Posted on 7/7/25 at 3:15 pm to
Probably only one asphalt supplier and they're taking forever to make it. Very likely getting it from a business along the river that only operates in the daytime to move trucks.
Posted by Aspercel
Member since Jan 2009
117492 posts
Posted on 7/7/25 at 3:16 pm to
That would probably end up being much faster than whatever the hell they are actually doing.
Posted by King of New Orleans
In front of The Hungry Tiger
Member since Jul 2011
11024 posts
Posted on 7/7/25 at 4:25 pm to
We’d be done if this was the case :lol.
first pageprev pagePage 1 of 1Next pagelast page
refresh

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on X, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookXInstagram