New I-10 Lake Charles Bridge Expected to Open to Traffic in February 2030

Posted on 11/3/25 at 7:26 am
Posted by ragincajun03
Member since Nov 2007
27083 posts
Posted on 11/3/25 at 7:26 am
quote:

The Health and Safety Council Louisiana and the West Calcasieu Chamber of Commerce hosted the Louisiana Bridge Builders in an information-sharing session on Tuesday at the HASC Louisiana location in Sulphur.

Construction on the new Interstate 10-Calcasieu River bridge will begin in March 2026. The project will be constructed in four segments simultaneously. Traffic is anticipated to shift to the new bridge in February 2030 and once the traffic has shifted the demolition will begin on the current bridge. The height of the bridge will be reduced from 152 feet to around 75-95 feet, which will make for a much smoother ride, according to Johnathan Hill, the public information officer for the I-10 Calcasieu Bridge Project. I-10 will remain open throughout construction.

There will be enhanced lighting on the bridge and the shape of the lighting will be in an arch, which mimics the arch of the current bridge. Four towers will also be on the new bridge and in the towers drivers will see replicas of the current pistols on the bridge. The pistols on the current bridge will be given to DOTD once the structure is demolished and they will decide what to do with them. The new bridge will have three travel lanes on each side, shoulders on each side of the roadway, and two auxiliary lanes to enter and exit the bridge. Final acceptance of the bridge will be December 2031.

The new bridge will include a toll. Tolling will start in August 2031 and it will be electronic. Noncommercial vehicles registered in the Southwest Louisiana region (Allen, Beauregard, Calcasieu, Cameron, and Jefferson Davis) will have a GeauxPass account with a discounted rate and a toll tag on the vehicle.

Final toll rates are not available at this time as the rates are subject to the Consumer Price Index each year.


LINK
Posted by stout
Porte du Lafitte
Member since Sep 2006
178874 posts
Posted on 11/3/25 at 7:27 am to
Here you can take a virtual drive on it


Posted by Horsemeat
Truckin' somewhere in the US
Member since Dec 2014
15060 posts
Posted on 11/3/25 at 7:27 am to
So in other words, 2065.
Posted by The Torch
DFW The Dub
Member since Aug 2014
26990 posts
Posted on 11/3/25 at 7:29 am to
quote:

Open to Traffic in February 2030




Five years to build a freaking bridge
Posted by CocomoLSU
Inside your dome.
Member since Feb 2004
155201 posts
Posted on 11/3/25 at 7:29 am to
quote:

Open to Traffic in February 2030

Posted by stout
Porte du Lafitte
Member since Sep 2006
178874 posts
Posted on 11/3/25 at 7:33 am to
quote:

Five years to build a freaking bridge



Over a swamp

If you watch the video it's a pretty big bridge but also a large interchange and there is way more to it. They have to demo a bunch of buildings and work around the existing bridge not to stop traffic. The logistics of keeping things flowing probably adds a lot of time. Then there's the whole swamp and river issue.

They also have to work with the refineries to work around/move all of that piping that currently runs all around the bridge.

Of course, no telling how much time EPA bullshite adds to it

It's already a nightmare traffic wise and they just started
This post was edited on 11/3/25 at 7:40 am
Posted by rowbear1922
Houston, TX
Member since Oct 2008
15742 posts
Posted on 11/3/25 at 7:35 am to
Now if only Baton Rouge could get one
Posted by Tarps99
Lafourche Parish
Member since Apr 2017
11251 posts
Posted on 11/3/25 at 7:35 am to
quote:

The new bridge will include a toll. Tolling will start in August 2031 and it will be electronic. Noncommercial vehicles registered in the Southwest Louisiana region (Allen, Beauregard, Calcasieu, Cameron, and Jefferson Davis) will have a GeauxPass account with a discounted rate and a toll tag on the vehicle.


Hopefully by then GeauxPass becomes intermodal with other state toll tags like TxTag and PikePass, otherwise out of state drivers will use the notices to line bird cages.
Posted by Hangover Haven
Metry
Member since Oct 2013
31726 posts
Posted on 11/3/25 at 7:40 am to
quote:

Here you can take a virtual drive on it


That video was so realistic, all those slow arse drivers in the left lane…
Posted by stout
Porte du Lafitte
Member since Sep 2006
178874 posts
Posted on 11/3/25 at 7:46 am to
quote:

That video was so realistic, all those slow arse drivers in the left lane…






Here is one of what will be the new Sampson ST overpasses exiting to Westlake as you come from the East





RIP large Welcome To Westlak sign





They're also building an exit that will take you to the front of the new Horseshoe
This post was edited on 11/3/25 at 7:47 am
Posted by jasonbr1975
Member since Sep 2024
835 posts
Posted on 11/3/25 at 7:48 am to
A bridge that high above the water and only a minimal 2.5' concrete wall! That's pretty scary. I would hope they either make the wall at least 5' tall or add some type of guard rail system.
Posted by CrappyPants
Member since Apr 2021
1017 posts
Posted on 11/3/25 at 7:48 am to
Is this replacing the bridge with the guns on it? The really tall one?
Posted by Loup
Ferriday
Member since Apr 2019
15518 posts
Posted on 11/3/25 at 7:49 am to
quote:

Here you can take a virtual drive on it



they should have added litter to make it more realistic
Posted by Breesus
House of the Rising Sun
Member since Jan 2010
69354 posts
Posted on 11/3/25 at 7:50 am to
It’ll never be ready in time
Posted by KamaCausey_LSU
Member since Apr 2013
16962 posts
Posted on 11/3/25 at 7:51 am to
quote:

Five years to build a freaking bridge

This one does have the added issue of multiple major industrial facilities having to move their pipelines.
Posted by stout
Porte du Lafitte
Member since Sep 2006
178874 posts
Posted on 11/3/25 at 7:52 am to
quote:


A bridge that high above the water and only a minimal 2.5' concrete wall! That's pretty scary. I would hope they either make the wall at least 5' tall or add some type of guard rail system.



You have obviously never taken the 210 bridge with its low guard rails and no shoulder.

It didn't even have working lights for 5 years since the hurricanes until last month they finally fixed them





This post was edited on 11/3/25 at 7:53 am
Posted by SlowFlowPro
With populists, expect populism
Member since Jan 2004
463653 posts
Posted on 11/3/25 at 7:53 am to
Damn Westlake is finally getting their overpass?
Posted by stout
Porte du Lafitte
Member since Sep 2006
178874 posts
Posted on 11/3/25 at 7:54 am to
quote:


Damn Westlake is finally getting their overpass?



Talking about Sampson St? Yea look at the other video I posted and it shows it
Posted by Horsemeat
Truckin' somewhere in the US
Member since Dec 2014
15060 posts
Posted on 11/3/25 at 7:55 am to
quote:

Hopefully by then GeauxPass becomes intermodal with other state toll tags like TxTag and PikePass, otherwise out of state drivers will use the notices to line bird cages.
Absolutely absurd that interstates are being tolled considering how its just another tax when you're already taxed in every single state on gasoline and diesel to fund highway infrastructure, but just like up Geauxpass with EZpass and be done with it.
Posted by sidewalkside
rent free in yo head
Member since Sep 2021
4145 posts
Posted on 11/3/25 at 7:55 am to
Even the virtual reality video had the assholes camped in the left lane impeding traffic
first pageprev pagePage 1 of 4Next pagelast page