Page 1
Page 1
Started By
Message

Microsoft Project Experts

Posted on 6/3/14 at 10:27 am
Posted by TigerMyth36
River Ridge
Member since Nov 2005
39727 posts
Posted on 6/3/14 at 10:27 am
Is it possible to show a range for task duration?

If yes, how?

Some tasks can take between 8 to 12 weeks depending on numerous outside variables so I don't want to lock myself down for one duration.

How do I best go about showing a range for duration?

I've used the almighty google but can't seem to find what I need.
Posted by CAD703X
Liberty Island
Member since Jul 2008
77930 posts
Posted on 6/3/14 at 10:30 am to
go back to the OT










































This post was edited on 6/3/14 at 10:31 am
Posted by TigerMyth36
River Ridge
Member since Nov 2005
39727 posts
Posted on 6/3/14 at 10:31 am to


Have a nice green steak .

This post was edited on 6/3/14 at 10:32 am
Posted by aaronb023
TeamBunt CEO
Member since Feb 2005
11774 posts
Posted on 6/3/14 at 10:37 am to
You can't do a ranged duration. You need fixed durations in order to come up with a critical path. Look up PERT. That might be something you could use to come up with the durations you are uncertain about.

Eta: it's not uncommon for durations in a schedule to change. You can always back it down or extend later


Eta2: can't believe I wasted my 10,000th post. I hate you
This post was edited on 6/3/14 at 10:40 am
Posted by TigerMyth36
River Ridge
Member since Nov 2005
39727 posts
Posted on 6/3/14 at 10:42 am to
quote:

Eta2: can't believe I wasted my 10,000th post. I hate you



Posted by Jackie Chan
Japan?
Member since Sep 2012
4681 posts
Posted on 6/3/14 at 10:43 am to



Yeah. Just mark the task time as an estimate and change it later if need be.
Posted by aaronb023
TeamBunt CEO
Member since Feb 2005
11774 posts
Posted on 6/3/14 at 10:48 am to
What kind of work are you scheduling? What are the outside variables that may change duration? Would that be a change order, or are you just figuring in contingency?
Posted by BayouBrawl
Junk Yard
Member since Aug 2012
1151 posts
Posted on 6/3/14 at 10:58 am to
Also, like I said in your other thread. Stop using an inferior product. Upgrade to P6. You can then set to "fixed units/time" and your duration will automatically calculate based on % Complete. Although this should never be used in a construction schedule. EPC in the engineering or procurement phase, it works fine.
Posted by TigerMyth36
River Ridge
Member since Nov 2005
39727 posts
Posted on 6/3/14 at 11:56 am to
The schedule is for permitting which can vary tremendously from project to project.

The PM doesn't want to be overly optimistic and then get nailed and he doesn't want to be pessimistic and piss off the client with a long duration.

quote:

Stop using an inferior product. Upgrade to P6.
Sure. I'll tell my CEO that we must upgrade immediately or I walk.

Just settled on sending them both short and long duration charts.
Posted by BayouBrawl
Junk Yard
Member since Aug 2012
1151 posts
Posted on 6/3/14 at 12:00 pm to
Instead of short and long durations, you can't show early and late dates? That would basically be the same thing. I don't know of any project scheduling program that will actually show multiple durations for one activity. If it is just for a chart for presentation, why not just fashion something in excel?
Posted by aaronb023
TeamBunt CEO
Member since Feb 2005
11774 posts
Posted on 6/3/14 at 12:01 pm to
Yeah that sucks. Sounds like you could piss off the client either way. Good luck
Posted by BayouBrawl
Junk Yard
Member since Aug 2012
1151 posts
Posted on 6/3/14 at 12:13 pm to
Just an Example:

Posted by aaronb023
TeamBunt CEO
Member since Feb 2005
11774 posts
Posted on 6/3/14 at 12:46 pm to
That's float though. Your example is a one day activity that isn't on the critical path.
Posted by BayouBrawl
Junk Yard
Member since Aug 2012
1151 posts
Posted on 6/3/14 at 1:07 pm to
Agreed. I was just showing it for the layout. Didn't feel like filtering anything out. You can set constraints to a finish milestone to drive those late dates by constraining float.
Posted by aaronb023
TeamBunt CEO
Member since Feb 2005
11774 posts
Posted on 6/3/14 at 1:29 pm to
My main point was that if his end date changes with the duration of the permitting activity then it is a critical path activity. You can't have float in a CP activity.

Eta: where you work at brawl? <--@cox.net
This post was edited on 6/3/14 at 1:33 pm
Posted by BayouBrawl
Junk Yard
Member since Aug 2012
1151 posts
Posted on 6/3/14 at 1:52 pm to
Agreed. That would be the point in constraining a finish milestone. His point was obviously just to show a presentation, not have a working schedule. If the point was to have a working schedule, he should simply change the duration type to fixed units/time. This would allow the duration (along with the finish date) to change whenever these variables come into play. That's why I feel that the short answer (for presentation purpose) is simply to constrain finish and allow the float to show as early and late dates.

ETA: YGM
This post was edited on 6/3/14 at 1:53 pm
first pageprev pagePage 1 of 1Next pagelast page
refresh

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on Twitter, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookTwitterInstagram